Great Britain sets out a phased reform of construction product rules for cable buyers

2026/11/25 14:08:23

A cable buyer pricing a building project in Manchester can still consider a lawfully CE-marked cable. In its 18 November response to the construction products white paper, the UK government set out a phased transition for Great Britain. It gave no common changeover date for cables covered by EN 50575.

Two dates to watch

The government plans to bring forward general safety regulations in 2027 for construction products outside the scope of a designated standard or technical assessment. It envisages at least 12 months between laying those regulations and their taking effect.

A separate Great Britain construction products regime is expected in 2028. A product moves across when a standard or assessment for it is adopted under the new framework. Until then, the existing 2011 regime continues for that product. The current Great Britain guidance recognises lawful CE marking in England, Scotland and Wales. Buyers sourcing for Northern Ireland should check the rules for that market separately.

What to ask for on a cable order

Start with the installation. A power, control or communications cable intended for permanent installation in construction works may fall within EN 50575 where reaction to fire is relevant. Record the intended use and the classification the project designer specified before comparing offers.

For example, suppose a bidder substitutes a 25 mm² cable for the 16 mm² cable on the original schedule. Ask for the declaration of performance (DoP) reference, the manufacturer's product-type identifier and the sizes covered. Check the offered construction against that scope and compare the declared reaction-to-fire class with the schedule, including any specified smoke, droplet and acidity subclasses. A shared trade name alone leaves that check open.

A life-safety circuit raises a separate question: how long must it continue to operate during a fire? Record the required circuit-integrity test and duration on a separate line and request evidence for the proposed construction. An EN 50575 reaction-to-fire classification describes the cable's contribution to fire and does not establish operating time.

For a cable enquiry, include the delivery market, intended use, cable type and size, quantity and the fire-performance wording from the project schedule.